New business electricity and gas connections

A new building, an empty unit with no live supply, or an operation that has outgrown its capacity all need work on the network before any supplier can help. Here is who does what, in what order, and where a supply contract fits in.

  • We reply by email
  • Forever Communications, part of Forever Group

In short

A new business electricity connection starts with an application to the local distribution network operator, which does the non-contestable work; contestable work can go to an accredited independent connection provider. Gas connections come from a gas transporter, a utility infrastructure provider or a supplier. Once connected, you need a supplier, a meter and a supply contract.

Ask about business energy supply for a new connection

Tell us your premises, meters and renewal date and we will reply by email with options.

Contact us

Who does what in a new connection

Getting energy to a site involves several different organisations. The one you pay for the connection is usually not the one that supplies your energy afterwards.

RoleElectricityGas
Owns and runs the networkThe distribution network operator (DNO) for your area, or in some places an independent distribution network operator (IDNO)The gas transporter for your area, or one of the transporters that build networks on new developments
Builds the new connectionThe DNO, with contestable work open to an independent connection provider (ICP)The gas transporter, or a utility infrastructure provider (UIP)
Supplies the energy and bills youA licensed electricity supplier you chooseA licensed gas supplier you choose
Fits the meterYour supplier, through a meter operator; half-hourly sites have a meter operator contractYour supplier, through its metering agent
Wiring or pipework inside the premisesYour electrical contractorA Gas Safe registered engineer

You do not choose your DNO or gas transporter: that depends on where the premises are. You can choose who carries out the contestable parts of a connection, and you choose your supplier. Network operators own the cables and pipes; suppliers sell the energy that runs through them. Both DNOs and IDNOs hold electricity distribution licences from Ofgem, and whichever owns the network serving your site, you still choose your own supplier.

Not sure which option suits you? Ask us

Tell us about your premises and usage and we will explain the options that fit.

Contact us

Getting a new electricity connection: the steps

  1. Work out what you need. List the equipment you will run, then have an electrician or consultant estimate the load in kVA and whether you need a single or three-phase supply.
  2. Apply to the network operator. The DNO for the area processes the application, decides the point of connection to its network and quotes for the work. Its published connection charging methodology sets out the information it needs and how it manages the request.
  3. Decide who does the contestable work. You can accept the DNO's quote for all of it, or ask an independent connection provider to quote for the contestable part. Non-contestable work stays with the DNO.
  4. Agree the terms and the works. Ofgem says connection charges must be cost reflective and calculated under the operator's connection charging methodology. If an ICP builds part of the connection, there is a Construction and Adoption Agreement with the network operator.
  5. Arrange a supplier and a meter. The new supply point gets its own MPAN. Before the supply goes live, a supplier needs to be registered to it, and the supplier arranges the meter through a meter operator.
  6. Agree a supply contract. Do this in good time so the new site does not start life on deemed rates.

Ofgem calls a change to an existing supply, such as moving from single to three-phase or increasing capacity, a service alteration. It follows the same route: you apply to the network operator, not to your supplier, and it quotes as it would for a new connection.

Contestable and non-contestable work

Competition in connections means some of the work does not have to be done by your network operator. Ofgem's connections guidance splits it like this:

Contestable: can be done by a third partyNon-contestable: only the network operator
Planning and design to the DNO's published specificationsProcessing your application
Obtaining consents and wayleavesDesigning and specifying reinforcement of the DNO's network
Providing the materialsDeciding the point of connection to the existing network
Trenching and other on-site works, including the cable route to the point of connectionApproving the design, then inspecting and testing the contestable works
Reinforcement and diversions fully funded by the customerConnecting the new assets to its network and energising the supply

Electrical contestable work must be carried out by a qualified independent connection provider registered with Lloyd's Register under the National Electricity Registration Scheme (NERS), which records the scope of work each provider is approved for. Civils work, such as trenching, can be done by you or your own contractor with the network operator's approval. Where a third party builds part of the connection, the network operator adopts the new assets under a Construction and Adoption Agreement.

Whether going to an ICP is worthwhile depends on the job, so ask for quotes on the same scope and compare what each one includes.

Want this looked at for your premises?

Tell us your sites, meters and renewal dates and we will reply by email with options.

Contact us

Single-phase, three-phase and capacity

Two technical questions shape any new or upgraded electricity supply.

Phases. Smaller premises are often supplied with a single-phase supply. Premises with heavier equipment, such as larger motors, commercial kitchens or several large heating or charging loads, may need three-phase. Your electrician can tell you what your equipment needs, and the network operator tells you what the network can provide at that location.

Capacity. The size of the connection is set as a capacity in kVA. For larger supplies this becomes the agreed capacity in your connection agreement, and on half-hourly sites the bill includes a daily capacity charge on that figure, whether you use it or not, plus excess charges if demand goes above it. Asking for far more than you need can cost money every day; asking for too little can mean another application later. Planning a realistic figure, with some allowance for growth, is worth the effort.

Larger supplies are usually metered half-hourly. Our guide to half-hourly meters explains what that means for metering and settlement.

Getting a new gas connection

Ofgem's factsheet for industrial and commercial premises describes three ways to get a one-off gas connection:

RouteHow it works
Gas transporterContact the gas transporter for the area with the details of the premises and the date you need the connection
Utility infrastructure provider (UIP)Employ a competent UIP to build the connection to the standards of the transporter that will adopt and maintain it. Lloyd's Register runs a voluntary registration scheme for this work, and some UIPs can also arrange the connection with the transporter as your agent
Licensed gas supplierA supplier arranges the connection through the transporter or a UIP and can pass on the charge, which may include an arrangement fee

Some gas transporters operate nationally rather than in one region; Ofgem's factsheet notes that they generally build new networks for housing estates and may also connect other premises. The pipework from your meter to your appliances is not part of the connection: Ofgem notes that a Gas Safe registered engineer must install it, and some UIPs offer to do this as well.

Once the connection is in, the supply point has an MPRN and a supplier arranges the meter. Larger gas sites must have advanced meters that the supplier can read remotely, and smaller sites can have smart meters. See MPRN number, smart meters for business and our guide to business gas.

Meters, supply numbers and the supply contract

A connection gives you a supply point; it does not give you energy on terms you have agreed. For that you need:

  • A supplier registered to the new supply point, which takes responsibility for metering and billing.
  • A meter, fitted by the supplier's meter operator or metering agents. Larger electricity sites need a half-hourly meter and a meter operator contract; smaller sites may get a smart meter. Our business electricity meters guide covers the options.
  • A supply number: an MPAN for each electricity supply, issued by the network operator, and an MPRN for each gas supply. Suppliers quote against these numbers. See MPAN number.
  • A supply contract, with a tariff type and term that suit how the new site will use energy. If energy is used before a contract is agreed, the supplier can charge deemed rates.

The supplier needs an estimate of annual consumption to quote. For a brand-new site there is no history, so a realistic estimate from your equipment list and opening hours helps.

If something goes wrong with a connection

For problems with connection works, start with the company you contracted with and use its complaints procedure. Ofgem's connections guidance sets out the next steps:

  • Energy Ombudsman: if a complaint about a network operator is unresolved after eight weeks, or reaches deadlock, domestic and microbusiness customers can take it to the Energy Ombudsman.
  • Ofgem determination: Ofgem may be able to determine some disputes with a network operator, such as the cost of a connection or the terms of a connection offer. Larger businesses can ask once the operator's complaints process is exhausted. Ofgem can usually determine a dispute up to 12 months after the connection is completed, although you will normally pay for the work up front.

Ofgem publishes guidance on how it determines disputes about connection to energy networks. Keep copies of the connection offer, correspondence and any agreed dates.

For problems with your supply contract or bills once the site is live, the route is the supplier's complaints process, then the Energy Ombudsman. See the Energy Ombudsman website for what it covers.

How we can help

We do not carry out connection works, and neither does Fidelity Energy: that is a job for the network operator and connection providers. What we can do is help you coordinate the energy side around the works. We help gather the details a supplier needs, explain metering and tariff choices for the new site, and introduce you to Fidelity Energy, an independent energy consultancy and broker that gets quotes from its network of business energy suppliers and arranges the supply contract you choose. Fidelity Energy also manages meter operator contracts for half-hourly sites and coordinates gas and electricity meter installations, and says it supports new site connections.

Planning a new site or a bigger supply? Contact us with the address, what you plan to run and where the works have got to. Already connected at another site and want to compare offers? See compare business energy on our sister site.

How Forever Communications helps with business gas and electricity

Forever Communications is part of Forever Group, which looks after phone systems, business mobiles and connectivity for UK organisations. For business electricity and gas, we work as an agent of Fidelity Energy, an independent business energy broker that prices your requirements with the suppliers on its panel. We are not an energy supplier, and neither is Fidelity Energy.

  • Make sense of your bills: we can help you read unit rates, standing charges, meter details and the other costs on your invoices
  • Like-for-like quotes: we help you gather your meter numbers, consumption and contract end dates so suppliers quote on the same basis
  • The right tariff type: we can talk you through fixed, flexible and pass-through contracts, green electricity and green gas options before you decide
  • Better timing: we help you plan a renewal ahead of your contract end date, or move off deemed and out-of-contract rates when you move premises
  • Your choice: you decide which quote, if any, to accept; prices and terms are set by the suppliers and confirmed at quote, including the broker commission

We work with offices, shops, hospitality, landlords, manufacturers and multi-site organisations. Send us a recent bill and we can take it from there.

Frequently asked questions

How do I get a new electricity connection for a business?

Work out the load and whether you need single or three-phase, then apply to the distribution network operator for the area, which quotes for the work. Contestable work can go to an accredited independent connection provider instead. Before the supply goes live, arrange a supplier, which arranges the meter, and agree a supply contract.

What is an independent connection provider?

An independent connection provider (ICP) is a company that can carry out the contestable part of a new electricity connection to the network operator's specifications, for the operator to adopt. Ofgem's guidance says electrical contestable work must be done by a provider registered with Lloyd's Register under the National Electricity Registration Scheme.

What is the difference between a DNO and an IDNO?

A DNO owns and runs the electricity distribution network for a region. An IDNO is an independent distribution network operator: it also holds an electricity distribution licence from Ofgem, and if your site is on an IDNO's network, the IDNO runs that part of it. Whichever owns the network serving your site, you still choose your own supplier.

What is contestable and non-contestable work?

Contestable work can be done by a third party, such as design to the DNO's specifications, consents, materials, trenching and on-site cabling, and customer-funded reinforcement. Non-contestable work only the network operator can do, such as processing the application, deciding the point of connection, designing reinforcement of its network and connecting and energising the supply.

Do I need an energy supplier before my new connection goes live?

Yes. A supplier needs to be registered to the new supply point to arrange the meter and bill you, so line one up before you start using energy. Agreeing a contract in good time also keeps the new site off deemed rates.

Still have a question about business energy supply for a new connection?

Ask us and a member of our team will reply by email.

Contact us

Next step

Want help with your business gas and electricity?

Tell Forever Communications what you need and we will come back to you by email with options and next steps.

  1. 1
    Tell us what you needA few lines is enough: your organisation, users or sites, and timescales.
  2. 2
    We read it and reply by emailWith options and clear next steps.
  3. 3
    You decideChoose the option that suits you and we take it from there.

Business Gas and Electric is a website of Forever Communications, part of Forever Group. We help businesses understand and arrange gas and electricity contracts.

Send a quick enquiry

We reply by email.

About: Business energy supply for a new connection

We only use these details to reply to your enquiry.

Talk to us about business energy supply for a new connection

We reply by email.

We only use these details to reply to your enquiry.
Talk to us aboutbusiness energy supply for a new connection
Contact us